UI Refresh #1821 — Documentation Hub

Updated: 2026-06-26 · Audited: 2026-06-26 · Work Item: AB#1821 · Last revised: 2026-06-10

Status: Component spec re-synced to Figma 2026-06-10 (decisions D1–D14). Implementation gated on Presentation Extraction (AB#2087).
Architecture: Blazor Hybrid + Hybrid SDUI (Path 2) — direction resolved 2026-06-08.
Target Launch: Fall 2026 (September–November)

Recommendation: Path 2 (Hybrid SDUI) — 31–38 weeks (Oct–Nov 2026). Can hit Fall 2026 deadline. Delivers 80% of SDUI value. Upgrade path to Path A (Full JSON SDUI) evaluable in 2027.

Architecture Paths Summary

PathEffortLaunchFall 2026?Best For
Path 2: Hybrid SDUI31–38 weeksOct–Nov 2026✅ RecommendedHit deadline, upgrade later
Path A: Full JSON SDUI52–60 weeksApr–Jun 2027❌ NoMaximum flexibility, 2027 launch
Path B: Blazor Hybrid20–24 weeksJul–Aug 2026✅ YesHTML from CMS, WebView acceptable
Path C: FlagstoneUI + SDUI56–64 weeksMay–Jul 2027❌ NoPixel-perfect (HIGH RISK v0.0.1)
Path D: Mixed Architecture28–34 weeksSep–Oct 2026⚠️ TightPragmatic balance, mixed UX OK

See UI Refresh Decision Matrix for detailed phase breakdowns.

Component Spec & Figma Re-sync (2026-06-10)

The component library spec, re-synced to the 2026-06-10 Figma revision. Start here for component work.

Not 100% delivered — more Figma designs may surface additional domain controls; the RCL extraction and per-component pages land with Presentation Extraction (AB#2087). Treat the spec as living.

Decision & Planning Documents

Communication Templates

Key Requirements (UAL MEC Communications)

Technical requirements: MEC customization (different branding/styling per MEC); dynamic updates (same-day without app store approval); offline support for key features; integration with AIRO (member info), Votenet (open votes), existing APIs.

Next Actions

  1. Finalize architecture decision (see Decision Matrix) — Path 2 recommended
  2. Schedule Communications questionnaire workshop (use Communications Questions)
  3. If choosing Path 2: begin SDUI foundation work Week 3–4 March (Remote ResourceDictionary loader, feature flag system, version management & caching)
  4. Ensure team capacity for 7.5–9.5 month effort

Document History