Updated: 2026-06-26 · Audited: 2026-06-26 · Work Item: AB#1821 · Last revised: 2026-06-10
Status: Component spec re-synced to Figma 2026-06-10 (decisions D1–D14). Implementation gated on Presentation Extraction (AB#2087). Architecture: Blazor Hybrid + Hybrid SDUI (Path 2) — direction resolved 2026-06-08. Target Launch: Fall 2026 (September–November)
Recommendation: Path 2 (Hybrid SDUI) — 31–38 weeks (Oct–Nov 2026). Can hit Fall 2026 deadline. Delivers 80% of SDUI value. Upgrade path to Path A (Full JSON SDUI) evaluable in 2027.
Design Tokens Reference — re-synced token set (semantic layer, status colors, MEC brand, spacing scale, typography)
Figma Sync Procedure — repeatable operating procedure for the next incremental sync
Not 100% delivered — more Figma designs may surface additional domain controls; the RCL extraction and per-component pages land with Presentation Extraction (AB#2087). Treat the spec as living.
Decision & Planning Documents
UI Refresh Decision Matrix — primary decision document with effort estimates for all 5 paths, phase-by-phase breakdowns, decision tree, and March 15, 2026 deadline analysis
Offline Contact Info — Accident Hotline, Intl SOS, Council Reps, Professional Standards, Legal, SOAR
Technical requirements: MEC customization (different branding/styling per MEC); dynamic updates (same-day without app store approval); offline support for key features; integration with AIRO (member info), Votenet (open votes), existing APIs.
Critical Path (Path 2 — Recommended)
March 2026 (Week 1–2): Architecture decision finalized
March 2026 (Week 3–4): SDUI foundation begins (6 weeks)
April–August 2026 (Months 2–5): Feature UI development (25–32 weeks)
September 2026 (Month 6): Internal testing, pilot prep
October 2026 (Month 7): UAL/DAL pilots launch
November 2026 (Month 8): Refinements based on feedback
Next Actions
Finalize architecture decision (see Decision Matrix) — Path 2 recommended